What should I do if additional work is discovered?

    Opening up a roof or a floor genuinely does reveal surprises. A calm, written process keeps a legitimate variation from becoming a dispute.

    Last reviewed 10 August 2026First published 10 August 2026Written by the TradesChecker editorial team

    The short answer

    Slow down and put it in writing. Ask to see it, ask why it must be done now, get the extra cost before the work happens, and confirm your agreement in a message. Most additional work is real; the disputes come from how it was handled, not whether it existed.

    Additional work is often genuine

    No one can see through a plaster wall or under a floor. Rotten joists, perished felt, undersized cables, missing lintels, asbestos-containing materials in older properties and failed damp-proof courses are all found routinely once work opens up. A contractor raising one of these is usually doing their job.

    The five-step process

    • Look at it. Ask to be shown the problem in place, and photograph it yourself before it is covered up.
    • Ask what happens if it is left. Some findings are safety-critical, some are advisable, some are simply an opportunity while access is open. They are not the same decision.
    • Get the cost in writing first — labour, materials and any extra days — before the work proceeds.
    • Check it independently. Price the additional element in the relevant calculator, or use Check My Quote on the revised total.
    • Confirm in writing. A short message saying 'I agree to the additional £X for Y as described' is enough, and it protects both of you.

    If you are not comfortable

    You are entitled to pause. Ask the contractor to make the area safe and to stop while you take a second opinion, particularly on structural, gas, electrical or asbestos matters. A confident contractor will not object to a specialist inspection.

    If you suspect asbestos-containing material, do not disturb it. Work with such materials is subject to specific controls and, for higher-risk material, must be carried out by a licensed contractor. The Health and Safety Executive publishes guidance on this.

    Where the additional work is large enough to change the project, treat it as a new quotation rather than a note scribbled on the old one.

    Keep the record together

    • Dated photographs of what was found, before it is closed up.
    • The written variation, its price, and your written agreement.
    • Any revised completion date, since extra work usually costs time as well as money.
    • Receipts and certificates for the additional work, which you may need when you sell.

    Questions you can put to the tradesperson

    • “Can you show me the problem and let me photograph it?”
    • “What is the consequence of not doing this now?”
    • “What is the additional cost and how many extra days does it add?”

    These are ordinary questions. A contractor who is comfortable with their pricing will answer them without difficulty.

    Put this into practice

    Check My Quote

    Enter the quotation you have received and see whether it sits within or outside the expected range, and what may be missing from it.

    Open check my quote

    Cost calculators

    Build an indicative cost range for your own job and specification before you judge any quotation.

    Open cost calculators

    Compare quotations

    Put two or three quotations side by side on scope, VAT, materials, waste, access and payment terms rather than on the headline total.

    Open compare quotations

    Sources

    Checked on 10 August 2026. Rules, thresholds and scheme requirements change, so follow the link for the current position.

    General information, not advice on your own circumstances, and not a legal opinion. For help with a specific dispute, contact Citizens Advice or another free independent service.

    All help and protection guides

    Enter the quotation you have received and see whether it sits within or outside the expected range, and which items may be missing from it.

    What you can expect from us

    TradesChecker is an independent UK service. We help you understand a job, sense-check its likely cost and examine a quotation — we do not carry out the work and we do not sell your findings.

    Built for UK customers
    Prices, VAT treatment, certification and regional differences are all based on how work is priced in the United Kingdom.
    Estimates are indicative
    Our figures are a guide to help you plan and ask better questions. They are not a quotation, a survey or a valuation.
    Regional and job factors matter
    Specification, access, location, materials, VAT and site conditions all move real prices — sometimes well outside a typical range for good reason.
    Findings are not for sale
    Commercial relationships never influence what we report about a quotation. No one can pay to change a finding.

    Our assessments are informational and do not replace professional surveying, estimating, building-control or legal advice. How we source our data.