A typical UK back-garden makeover (patio, lawn, borders, fence) for a 60–80m² garden runs £6,000–£14,000 in 2026 depending on materials, access and how much is being torn out first.
Quotes vary hugely — same garden, three landscapers, can land between £5,500 and £18,000. Below are the per-element prices to benchmark each line against.
Compare your quote against typical UK regional prices — free, no sign-up.
Per-element UK pricing
Indian sandstone patio: £110–£160/m² supplied and laid. Porcelain patio: £140–£200/m². Composite decking: £180–£260/m². Real timber decking: £120–£170/m². Artificial grass: £40–£75/m². Real turf: £8–£14/m² supplied and laid.
Closeboard fence panels: £90–£140 per 6ft panel installed. Concrete-post fences run £30–£50 more per panel than timber-post.
What inflates a landscaping quote
Poor rear access (no side gate, must wheel through the house) adds £400–£1,200 to the labour. Skip and waste disposal for a full strip-out runs £350–£900. Drainage to a soakaway: £600–£1,500.
Tree removal, root grinding and topsoil import are commonly bundled vaguely — always ask for them as separate lines with quantities.
Where overcharging happens
Patio sub-base is the #1 corner-cutting area: spec should be 100mm+ MOT Type 1 hardcore, compacted in layers, with a full mortar bed for sandstone or porcelain. A patio laid on sand alone will move and crack within 18 months.
Watch for vague 'planting and finishing' lines — should be itemised with plant counts. Check the quote includes all jointing (resin or mortar) and edge restraints.
Realistic timelines
A 30m² patio with a proper sub-base takes 4–6 days. A full back-garden makeover (patio, lawn, fencing, planting) for an 80m² garden takes 2–3 weeks.
Anyone promising a full makeover in under a week is cutting corners on the sub-base, drainage or fixings.
Real UK price examples
Typical 2026 ranges based on submitted quotes and regional pricing data.
Key takeaways
- Get 3 itemised quotes broken down by element (patio, fence, lawn, planting, waste).
- Specify the sub-base depth (100mm+ MOT Type 1) and jointing material in writing.
- Don't accept patios laid on sand alone — they will fail.
- Confirm rear access and waste-removal lines are quoted separately, not bundled.
- Allow 2–3 weeks for an 80m² full makeover. Anything under a week is rushed.
Frequently asked questions
Doing some of the prep or finishing yourself? Browse tools and materials at Tooled Up.
Affiliate link
Check your quote against UK pricing data
Get a fair-price range for your job in 30 seconds. Free, independent, no sign-up.
Related guides
More honest UK pricing guides you might find useful.

Volatile material prices, fake bookings, fuel costs and brutal cash-flow pressure are pushing UK trades from 'pay on completion' to upfront deposits. Here's what's really driving it — and what's reasonable.

Real 2026 UK prices for full roof replacements — concrete tile, clay tile and slate — plus the scaffolding, felt and battening costs that swing the final bill.

Real 2026 UK prices for air source heat pump installs — unit, hot water cylinder, radiator upgrades and the BUS grant — plus what 'heat pump ready' actually means.

Real 2026 UK prices for converting a single or double garage into living space — insulation, floor build-up, windows and the building regs work that's not optional.